THE FIRST CONCRETE

Yesterday received Weekly Report W4, what means that four weeks of work are now done. This week we will meet at the project with the contractor & architect to review all and sign the progress.

This is the status:
21 November 2022 to 4 December 2022

Plan progress of the week 2.21%
Cumulative progress of plan 5.14%
Realization progress of the week 5.62%
Realized cumulative progress of 9.49%
Deviation 4.35%

Today the first serious batch of concrete has been poured. After two samples of concrete all looked good and the next layer of building is being set. Walls are growing and the trenches down the cabin are getting lower. Another day of great weather and progress.